Cross Insurance Center Updates
Construction is 92% complete
The following outlines summarizes recent and upcoming building construction activity: ARENA 1) Event Level - Concrete floor finishing completed...
Installation of all seating is nearly complete
Progress on the Cross Insurance Center continues to be good and is consistent with the original project schedule. Most outside building construction work and sitework has been suspended for...
Assembly of the retractable telescopic seating system has begun
SITEWORK 1) Building sewer service connection were installed on both Buck Street and Dutton Street. 2) Grading of the Park area continued, with...
Locker rooms and adjacent show support rooms are finishing up quickly, and tile installation will begin shortly
Some highlights of work undertaken in the last month include the following: STRUCTURAL and EXTERIOR 1) All structural steel has now been completed. 2) All roof...
In a few areas, final finishes are being applied to drywall surfaces, metalwork, etc
STRUCTURAL AND EXTERIOR 1) Except for a very few minor steel members in the Conference Center entrances, all structural steel is done. 2) Work continued on finishing...
Much of work now focused on the interior
1) All structural steel complete, except for a few members at the “Rotunda” entrance to the Conference Center. 2) Roof System was substantially completed 3) All interior structural slabs...
Roof system nearly complete
Some highlights include the following: STRUCTURAL AND EXTERIOR 1) All major structural steel is complete - wall sheathing is nearing completion for back of house (Buck St/Loading)...
City of Bangor Announces Agreement on Naming Rights for New Arena and Convention Center
“What an amazing day for Bangor. A hearty thank you to the Cross Family and Cross Insurance for their belief in not only this project but in the future of Bangor,” said Mayor Cary Weston. “The energy...
Considerable amount of work completed during the month of June
Some highlights include the following: STRUCTURAL and EXTERIOR 1) With all major structural steel now complete, roof and wall sheathing for the Arena "back...
Much of stone and brick exterior work is complete
STRUCTURAL and EXTERIOR All major structural framing for the Convention Center and the "back of house" portion of the Arena have been completed. This is the remainder...
Heavy Structural Framing is Complete
Construction progress continues to be excellent and within the "critical path" master schedule Cianbro developed for the project. Some highlights include the following:...
Construction progress of the Bangor Events Center continues to be excellent
Over the past month much progress has been made. This has involved a lot of highly visible work.............most notably, much of the Arena roof framing and more of the arena "bowl”. ...
Primary seating areas in the arena bowl are taking shape
Clearly the unusually mild winter weather has been helpful. As can be readily seen by driving by or viewing progress on the web cam, a considerable part of the arena building framing has been erected....
The arena is starting to emerge
The foundation for the Arena is essentially complete now, with approximately 4000 CY of reinforced concrete placed to date. The floor slab will be constructed this spring. Work has...
Foundation work nears completion
Work this month has primarily involved continued construction of foundation structures and walls plus installation of more underground utilities, conduit runs and similar facilities. ...
Foundation work is 25% complete
Ongoing work primarily involves a continuation of foundation and footing construction and installation of various underground utilities throughout the site. Total foundation work...
Sitework and Utility Installations
Work to date on the project has primarily involved sitework, onsite utility installations and foundation work. Shafts for elevator hydraulic actuation equipment have also been drilled and capped. ...