Bangor City Hall
73 Harlow Street, Bangor, ME 04401

Phone:
207.992.4200

Business Hours:
Monday - Friday
8:00AM - 4:30PM

Transit Center

Friday, June 24, 2022:

Transit Center:  Crews continued working on masonry on the outside of the building, as well as utility installation on the inside of the building.

Water Street:  Eastwood Constractors installed approximately 150 L.F. of 24” storm drain.  They are also working with Bangor Gas to reroute a 2” gas main on Water Street.

Thursday, June 16, 2022

Work continues on the Bangor Area Transit Center, with masonry being placed on the outside of the building. 

Inside the building, contractors have been installing electrical components, as well as plumbing and insulation.

The Water Street Sewer separation project continues to move forward, with approximately 500 feet of new sewer main already installed.

Eastwood Contractors are now working on the installation of stormwater drainage.

Friday, May 20, 2022

 

Contractors began installing roof panels and steel stud installation for interior walls. They are making good progress at this time, and will continue next week.

Wednesday, April 13, 2022

 

Thursday, February 17, 2022

Monday, February 7, 2022

Friday, October 22, 2021

 

 

 

 


Tuesday September 21, 2021

Construction began this week on the Bangor Area Transit Center that is located in Pickering Square.

The proposed Transit Center is a 2,200 square foot single story building and includes an indoor waiting area, administrative space, public bathrooms, a bus drivers’ room, and security office. The exterior of the building includes covered waiting areas, outdoor seating, lighting, and accessible passenger loading areas.

Benchmark Construction, of Westbrook, Maine was the selected Contractor to complete the project. The construction cost for the Transit Center is about $3.45 million. Funding for the project is provided through grants from the Federal Transit Administration and the Maine Department of Transportation with the City of Bangor and local Community Connector partners providing a 20 percent match.

The expected completion date for the project is December 2022, subject to change. The Community Connector bus service will maintain continuous operation during the construction of the new Transit Center.


On September 21, 2020, Artifex architects & engineers of Bangor, was awarded the design contract for the Bangor Transit Center at Pickering Square. The project involves designing a new modern Transit Center building and canopy that will focus on the transit rider with amenities that improve the passenger experience.

The new facility will incorporate ADA accessible elements that will enhance the usability and mobility to all users. The proposed amenities will include heat and air conditioning, an enclosed waiting area, outside shelters and interactive schedule information kiosks, public restrooms and bus operators' break room and private restroom.

 

On Monday December 14, 2020 a pre-council meeting was held to review and select a concept to move forward with. The council selected the Courtyard building and canopy concept as shown in the images below. Artifex will now begin the design development stage to advance the selected conceptual design into the final design phase such that project budgets can be further refined. Once a final plan and budget is approved by council construction documents will be developed for contractor bidding.

Construction is anticipated to begin in the summer of 2021.

 

Updates will be provided to report on the progress of the project periodically.